Renovation of Arrivals 2A proceeds

Article published
20.4.2015 at 09:59
Archived
Kaksi matkustajaa poistuu saapuvien 2A aulasta.
Responsibility Travel
The renovation work in the Arrivals 2A lobby and the baggage claim lobby Exit 2A continues as planned. Services in Arrivals 2A will move to their permanent locations, the building of the new restaurant area will continue, and the second phase of the arrival services upgrade will commence during spring 2015.

Tourist information, money exchange and taxi service point to their permanent locations

The service points in Arrivals 2A lobby in Terminal 2 will begin to move to their permanent locations towards the end of April. The tourist information desk will move to its permanent location at the end of April. The ChangeGroup money exchange and the taxi service point will move to their new locations in May.

Tourist information, money exchange and the taxi service point can be found in the Arrivals 2A lobby both now and in future.

Richie’s Gourmet Hot Dogs will be temporarily relocated about 50 meters from its current location from the beginning of May until the end of June.

Building Burger King and other restaurants continues

Additions to the restaurant services in the Arrivals 2A lobby will emerge in summer 2015. For example, Burger King will open its doors in the 2A lobby in June. The entire restaurant section is expected to be ready in early autumn 2015.

Renovation of arrival services at Exit 2A soon completed

The renovation of the arrival service premises in the baggage claim lobby Exit 2A in Terminal 2 started in January 2015.

The goal of the renewal is to improve the functionality of the arrival services and to renew the facilities to meet the needs of growing passenger volumes.

The goal of the renewal is to improve the functionality of the arrival services and to renew the facilities to meet the needs of growing passenger volumes.

The renovation is conducted in two phases. The first phase is currently ongoing, and the second phase will begin in the beginning of May. The renovation is expected to be completed in June 2015.

 

Noise and dust possible in Exit 2A during the construction work

The goal is to carry out the work during off-peak hours, whenever possible.

The aim is to minimise the noise and dust problems, for example, by vacuuming the construction areas daily and by using tools with dust extraction systems in areas where there will be dust.

During the renovation, there will be fewer arrival service desks available than usual at Exit 2A. As a result, the service may become congested during busy hours.

Arrivals 2A to become more functional and pleasant

The services at Arrivals 2A will be centralised to make it easier for arriving passengers to access the services and leave the airport. Additionally, a large restaurant complex with a wide range of restaurants will be built in the lobby.

After the renovation, the range of services at the airport for arriving passengers and those picking up and dropping off passengers will be broadened.

The renovation work in the Arrivals 2A lobby began in November 2014. After the renovation, the range of services at the airport for arriving passengers and those picking up and dropping off passengers will be broadened.

The services at Arrivals 2A will be centralised to make it easier for arriving passengers to access the services and leave the airport. Additionally, a new, large restaurant complex with a wide range of restaurants will be built in the lobby.

The goal is to carry out all renovation work in a way that causes as little disturbance to airport customers as possible. We apologise for any inconvenience the renovation may cause.